How it is calculated
- Volume: width × length × depth for slabs; π × (diameter/2)² × height for round columns. Imperial inputs are converted to metric (1 ft = 0.3048 m, 1 in = 25.4 mm) and results are shown in both cubic yards and m³.
- Waste: the percentage you enter is added to the volume (5–10% is common on small jobs).
- Dry volume: wet volume × 1.54.
- Shares: the dry volume is split by the mix ratio. A 1 : 2 : 4 mix has 7 parts: cement 1/7, sand 2/7, gravel 4/7.
- Cement weight: cement volume × 1440 kg/m³, divided by the bag weight and rounded up.
Example: a 5 m × 4 m slab, 15 cm deep, is 3 m³ (3.92 yd³). With a 1 : 2 : 4 mix that needs 4.62 m³ of dry material, of which 0.66 m³ is cement: 950.4 kg, or 39 bags of 25 kg. Sand is 1.32 m³ and gravel 2.64 m³.
Materials for 1 m³ (no waste, 25 kg bags)
| Mix | Cement | Sand | Gravel |
|---|---|---|---|
| 1 : 1.5 : 3 (approx. M20) | 403.2 kg (17 bags) | 0.42 m³ | 0.84 m³ |
| 1 : 2 : 4 (approx. M15) | 316.8 kg (13 bags) | 0.44 m³ | 0.88 m³ |
| 1 : 3 : 6 (lean concrete, M10) | 221.8 kg (9 bags) | 0.46 m³ | 0.92 m³ |
Sand and gravel tonnage uses typical dry bulk densities of 1540 and 1500 kg/m³; moisture and grading change these. Water is not included: keep the water-cement ratio around 0.5 and adjust for workability.